Workover activity in Italy with Total E&P
Technical supervision for the last Workover with Total E&P in Italy on GG2 well.
SPOT has provided the 4 Company mans to supervise the Workover activity during the complete duration of the intervention. A plugged dual ESP completion string was pulled out from 4200 mMD and replaced with a 4-1/2” tubing temporary completion string. The well pas is located at 1052 m/MSL, and the job was performed during winter season, under adverse meteo conditions with a lot of snow and strong wind.